FY 2013-14 ADA Transition Plan Update

In Fiscal Year 2013-14 the Transition Plan identified improving accessibility primarily along Colma Blvd, Mission Road and the Sterling Park Recreation Center. The estimated cost to remove these barriers was $71,500. The actual barrier removal cost was approximately $84,255.

Check the Physical Barrier’s Removed document that details the accessibility issue, action taken, and the estimated and actual cost of removing the barrier.

For information regarding accessible services at Town Hall please contact the ADA Coordinator at 650-997-8300.